Colorado Daily Status Report: June 27, 2024

Colorado Daily Status Report Link to the full report.

 

Graphic showing all FEMA lifelines as green and stable.

 

State Emergency Operations Center (SEOC) Status Level 2

SEOC continues to support of the following: U.S. 50 Blue Mesa Reservoir Middle Bridge Closure and monitoring the Oak Ridge Fire.

SEOC is operational Monday through Friday from 8 a.m. to 5 p.m.

U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

Information links for the bridge closure. 

Oak Ridge Fire

Information links for the fire:

 

Colorado Daily Status Report: June 25, 2024

Colorado Daily Status Report Link to the full report.

 

Graphic showing all FEMA lifelines as green and stable.

 

State Emergency Operations Center (SEOC) Status Level 2

SEOC continues to support of the following: U.S. 50 Blue Mesa Reservoir Middle Bridge Closure and monitoring the Oak Ridge Fire.

SEOC is operational Monday through Friday from 8 a.m. to 5 p.m.

U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

Information links for the bridge closure. 

Oak Ridge Fire

Information links for the fire:

Colorado Daily Status Report: June 24, 2024

Colorado Daily Status Report Link to the full report.

 

Graphic showing all FEMA lifelines as green and stable.

 

State Emergency Operations Center (SEOC) Status Level 2

SEOC continues to support of the following: U.S. 50 Blue Mesa Reservoir Middle Bridge Closure and monitoring the Interlaken Fire in Lake County

SEOC is operational Monday through Friday from 8 a.m. to 5 p.m.

U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

Information links for the bridge closure. 

Colorado Daily Status Report: June 14, 2024

Colorado Daily Status Report Link to the full report.

 

Graphic showing all FEMA lifelines as green and stable.

 

State Emergency Operations Center (SEOC) Status Level 2

SEOC continues to support of the following: U.S. 50 Blue Mesa Reservoir Middle Bridge Closure and monitoring the Interlaken Fire in Lake County

SEOC is operational Monday through Friday from 8 a.m. to 5 p.m.

U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

Information links for the bridge closure. 

Interlaken Fire 

Colorado Daily Status Report: June 13, 2024

Colorado Daily Status Report Link to the full report.

 

Graphic showing all FEMA lifelines as green and stable.

 

State Emergency Operations Center (SEOC) Status Level 2

SEOC continues to support of the following: U.S. 50 Blue Mesa Reservoir Middle Bridge Closure and monitoring the Interlaken Fire in Lake County

SEOC is operational Monday through Friday from 8 a.m. to 5 p.m.

U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

Information links for the bridge closure. 

 

Colorado Daily Status Report: June 12, 2024

Colorado Daily Status Report Link to the full report.

 

Graphic showing all FEMA lifelines as green and stable.

 

State Emergency Operations Center (SEOC) Status Level 2

SEOC continues to support of the following: U.S. 50 Blue Mesa Reservoir Middle Bridge Closure and monitoring the Interlaken Fire in Lake County

SEOC is operational Monday through Friday from 8 a.m. to 5 p.m.

U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

Information links for the bridge closure. 

Colorado Daily Status Report: June 11, 2024

Colorado Daily Status Report Link to the full report.

Graphic showing all FEMA lifelines as green and stable.

 

State Emergency Operations Center (SEOC) Status Level 2

SEOC continues to support of the following: U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

SEOC is operational Monday through Friday from 8 a.m. to 5 p.m.

U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

Information links for the bridge closure. 

June 11 Public Meeting

    • CDOT will be hosting a hybrid public meeting regarding the US 50 Blue Mesa Reservoir Bridge closure.  Join CDOT, Kiewit Construction, and Gunnison County for the latest information about the upcoming limited opening, inspections, repairs, and alternate routes. 
    • Tuesday, June 11, 2024
    • Located at the Gunnison Courthouse (200 E Virginia Ave, Gunnison) 
    • Time: 6:30 to 8 p.m.
    • To join online, go to bit.ly/US50VirtualMeeting
       

Colorado Daily Status Report: June 10, 2024

Colorado Daily Status Report Link to the full report.

Graphic showing all FEMA lifelines as green and stable.

 

State Emergency Operations Center (SEOC) Status Level 2

SEOC continues to support of the following: U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

SEOC is operational Monday through Friday from 8 a.m. to 5 p.m.

U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

Information links for the bridge closure. 

Colorado Daily Status Report: June 7, 2024

Colorado Daily Status Report Link to the full report.

Graphic showing all FEMA lifelines as green and stable.

 

State Emergency Operations Center (SEOC) Status Level 2

SEOC continues to support of the following: U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

SEOC is operational Monday through Friday from 8 a.m. to 5 p.m.

U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

Information links for the bridge closure. 

Colorado Daily Status Report: June 6, 2024

 Colorado Daily Status Report Link to the full report.

Graphic showing all FEMA lifelines as green and stable.

 

State Emergency Operations Center (SEOC) Status Level 2

SEOC continues to support of the following: U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

SEOC is operational Monday through Friday from 8 a.m. to 5 p.m.

U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

Information links for the bridge closure. 

Colorado Daily Status Report: June 5, 2024

Colorado Daily Status Report Link to the full report.

Graphic showing all FEMA lifelines as green and stable.

 

State Emergency Operations Center (SEOC) Status Level 2

SEOC continues to support of the following: U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

SEOC is operational Monday through Friday from 8 a.m. to 5 p.m.

U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

Information links for the bridge closure. 

Colorado Daily Status Report: June 4, 2024

Colorado Daily Status Report Link to the full report.

Graphic showing all FEMA lifelines as green and stable.

 

State Emergency Operations Center (SEOC) Status Level 2

SEOC continues to support of the following: U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

SEOC is operational Monday through Friday from 8 a.m. to 5 p.m.

U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

Information links for the bridge closure.  Lt. Governor Primavera verbally declared a disaster emergency on April 23, 2024 to support the event.

 

Colorado Daily Status Report: June 3, 2024

Colorado Daily Status Report Link to the full report.

Graphic showing all FEMA lifelines as green and stable.

 

State Emergency Operations Center (SEOC) Status Level 2

SEOC continues to support of the following: U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

SEOC is operational Monday through Friday from 8 a.m. to 5 p.m.

U.S. 50 Blue Mesa Reservoir Middle Bridge Closure

Information links for the bridge closure.  Lt. Governor Primavera verbally declared a disaster emergency on April 23, 2024 to support the event.